Project Profile
Grant Implementation Signing Date
25th May 2023
Project Start Date
25th May 2023
Project End Date
30th October 2024
Completion Time (Duration)
17 Months
- Thematic Area: Flood Resilience
- Plan: NDMP, SFDRR, NFPP-IV
- Entity: Public
Loading..........
The Data is Not Available
Indicators
Achievement
No. of people vulnerable to the negative impacts of multiple natural hazards better protected and became resilient
Beneficiaries Direct = 460000 Individuals
Hectare of land protected (agriculture / non-agriculture) against negative impacts of multiple natural disasters
Agriculture Land = 950
Non-agriculture Land = 1200
Number of flood protection/water conservation structures and river training works constructed / improved (levees, dikes,
GLOF schemes etc.)
Spin Karez:
Rehabilitation of Dam Body.
Rehabilitation Spillway
Rehabilitation Guide Channel.
Mandoki Check Dam:
Restoration of Dam Body
Restoration of Pipe Outlet.
Small Dam Aghberg:
Only Spillway Rehabilitation.
Ghundak Karez Dam:
Only Spillway Rehabilitation.
Khalaka Check Dam Kuchlak.
Only Spillway Rehabilitation.
Murghi Kotal Dam:
Dam body
Spillway
Restoration of Shagai-I:
Dam body
Pipe outlet 6’
Spillway
M.S Pipe outlet 12’
U/S Gabian Check Dam.
Restoration of Habib Dara II:
Dam Body
Spillway Retaining Wall & Wing Walls
Pipe outlet
Core Wall
Restoration of Brewery Dam:
Dam Body
Spillway
Pipe outlet
Key wall and Catch Drain
Restoration of KACH Dam:
Dam body
Core wall
KM of critical flood disaster risk reduction structures retrofitted and/or reconstructed
Total length = 3.774 KM
- Funding Ratio :
100% NDRMF Share
Project Size: Large (>500)
- Status :
Completed
Main objective of the project is to protect the lives and livelihoods of the local population along with critical infrastructure. After successful execution of the project, the following prime objectives will be achieved:
- Restoration & Strengthening of Dams.
- Slope Stabilization.
- Enhancement of Life of Dams.
- Significant Ground Water Recharge.
- Protection of Population from flood havoc.
- Protection of Physical Infrastructure.
- Protection of Precious Human Lives.
- Drought mitigation through restoration and strengthening and enhancement of life of Dams.
- The interventions have been contributing in Significant Ground water recharge.
- Slope stabilization was ensured by the project interventions.
- Protection of lives and livelihoods of the local population.
- Protection of physical infrastructure.
A more disaster-resilient Baluchistan with reduced socioeconomic and fiscal vulnerability to natural hazards and climate variability and change.
Baluchistan (District Quetta).
Geographical Coverage
Project Gallery
INTERVENTIONS
PROVINCE
DISTRICT
PROJECT SITE
Spin Karez:
Rehabilitation of Dam Body.
Rehabilitation Spillway
Rehabilitation Guide Channel.
Baluchistan
Quetta
Spin Karez
Mandoki Check Dam:
Restoration of Dam Body
Restoration of Pipe Outlet.
Baluchistan
Quetta
Mandoki
Small Dam Aghberg:
Only Spillway Rehabilitation.
Baluchistan
Quetta
Aghberg
Ghundak Karez Dam:
Only Spillway Rehabilitation.
Baluchistan
Quetta
Ghundak Karez
Khalaka Check Dam Kuchlak:
Only Spillway Rehabilitation.
Baluchistan
Quetta
Kuchlak
Murghi Kotal Dam:
Dam body
Spillway
Baluchistan
Quetta
Murghi Kotal
Restoration of Shagai-I:
Dam body
Pipe outlet 6’
Spillway
M.S Pipe outlet 12’
U/S Gabian Check Dam.
Baluchistan
Quetta
Shagai
Restoration of Habib Dara II:
Dam Body
Spillway Retaining Wall & Wing Walls
Pipe outlet
Core Wall
Baluchistan
Quetta
Habib Dara
Restoration of Brewery Dam:
Dam Body
Spillway
Pipe outlet
Key wall and Catch Drain
Baluchistan
Quetta
Brewery
Restoration of KACH Dam:
Dam body
Core wall
Baluchistan
Quetta
KACH
Targeted Beneficiary
The project area has been prone to the floods during heavy rains. The flash floods from hill torrents result in devastation engulfing almost entire areas because of high velocity and magnitude. The rainfall in July and August 2022 broke all the previous records and the high magnitude flash floods proved to be a catastrophe causing irreparable loss to precious human lives and public and private infrastructure. The sites were severely damaged during the flash floods and required immediate restoration. Main objective of the project was to protect the lives and livelihoods of the local population along with critical infrastructure. Following schemes were completed under the project:
Sr. No.
Sub-Scheme Name
01
Spin Karez Dam Quetta.
02
Mandoki Check Dam Quetta.
03
Small Dam Aghberg.
04
Ghundak Karez Check Dam.
05
Khalaka Check Dam Jalogeer Kuchlak.
06
Murghi Kotal Dam Kuchlak.
07
Shagai-I DAM.
08
Shagai-II DAM.
09
Habib Dara-II.
10
Brewery Delay Action Dam (Kar Khasa).
11
Kach Delay Action Dam.