Building Resilience of Damaged Flood Mitigation Structures along River Indus in Sindh Province

Building Resilience of Damaged Flood Mitigation Structures along River Indus in Sindh Province.

Project Code:  GR-01-2023
Fund Implementing Partner: Sindh Irrigation Department

Project Profile

Grant Implementation Signing Date

19th May 2023

Project Start Date

19th May 2023

Project End Date

30th September 2024

Completion Time (Duration)

16 Months

  • Thematic Area: Flood Resilience
  • Plan: NDMP, SFDRR, NFPP-IV
  • Entity: Public

Loading..........

The Data is Not Available

Indicators

Achievement

Number of flood protection/water conservation structures and river training works constructed/improved (levees, dikes, GLOF schemes etc.)

Bakhri Loop and SM Bund
Total Structures= 7
Studs = 5 Nos.
Rehabilitation Bakhri Loop Bund 0/0 to 0/1
Rehabilitation SM Bund at mile 12/0-12/7

Hala and SM Bund
Total Structures= 5
Studs = 3 Nos.
Hala Spur S.M Bund at mile 142/3
Hala Spur S.M Bund at mile 142/5

SM Bund
Total Structures = 2 Nos.
Rehabilitation of 1 No. Stone Studs
Rehabilitation of Stone Pitching at location 70/7 – 72/0

Surjani Complex Bund
Total structures = 6 Nos.
Rehabilitation of 2 Nos. Stone Studs
Rehabilitation of T-Head Spurs
Rehabilitation of 3.4 km bund

KM of critical flood disaster risk reduction structures retrofitted and/or reconstructed.

11.246 KM

  • Funding Ratio :

100% NDRMF Share

    Project Size: Large (>500)

0 M
Total Project Cost
  • Status :
Completed
Project Objective

The objective of this project is to contribute towards disaster-resilient Sindh with reduced socioeconomic and fiscal vulnerability to natural hazards and climate variability and change.

Project Outcome
  • Contributed in resilience building by protected population, livelihoods and environment.
  • The project protected populated districts of Shaheed Benazir Abad, Matiari, Sukkur, Naushero, Feroze and Sujawal.
  • Protected 127,036 Ha fertile land from floods.
  • Protected infrastructure including industries, railway line, highways, irrigation networks, schools, houses and public health infrastructure from floods.
Project Impact

Improved flood protection infrastructure to reduce Flooding associated impacts and incidents.

Geographical Coverage

Sindh (District Shaheed Benazirabad, Naushero feroz, Sajawal, Matiari).

Geographical Coverage

Project Gallery

INTERVENTIONS

PROVINCE

DISTRICT

PROJECT SITE

Bakhri Loop and SM Bund
Rehabilitation of Bakhri Loop Bund from mile 0/0 to 0/1
Rehabilitation of SM Bund at mile 12/0 to12/7
Construction of Stud mile 12/0 to 12/7 along SM Bund
Construction of Apron mile 12/0 to 12/7 along SM Bund
Construction of Stud/Apron mile 0/0 to 0/1 along Bakhri Loop Bund

Sindh

Naushero Feroz

Bakhri Loop and SM Bund

Hala and SM Bund
Construction 3 Nos. of Stone Studs
Construction of Spur at Hala and S.M Bund Mile at mile 142/3
Construction of Spur at Hala and S.M Bund Mile 142/5

Sindh

Matiari

Hala and SM Bund

SM Bund
Construction of Stone Studs
Rehabilitation of Bund and Stone Pitching at location 70/7 – 72/0
Rehabilitation of Stone Apron of 2.1 miles

Sindh

Shaheed Benazirabad

SM Bund

Surjani Complex Bund
Rehabilitation of 2 Nos. Stone Studs
Rehabilitation of Spur at Mile 2/5
Rehabilitation of Spur at Mile 3/1
Rehabilitation of Spur at Mile 0/3
Rehabilitation of Spur at Mile 1/1
Rehabilitation of Spur at Mile 1/5
Rehabilitation of 3.4 km Bund /Stone Apron and Stone Pitching

Sindh

Sujawal

Surjani Bund

Targeted Beneficiary

Total Beneficiary
Direct Beneficiaries
Project Description

Floods 2022 inflicted heavy losses of lives, livelihoods and infrastructure across Pakistan and Sindh was one of the worst affected province. A total of 10 million people affected in 30 districts. The worst affected areas remained inundated for months due to absence of natural drainage pathways leaving behind a vast magnitude of damaged public infrastructure, agriculture land and houses of people. The irrigation department government of Sindh submitted proposals or reconstruction and rehabilitation of infrastructure schemes that received major damages/losses during the monsoon floods 2022 in district Shaheed Benazirabad, Naushero Feroze, Sujawal and Matiari. Post completion of the project, the live, livelihood, private and public infrastructures will be saved and enhance resilience against floods in the area. The list of schemes implemented under the project is as follows:

Sr. No.

Sub-Scheme Name

01

Rehabilitation/Reconstruction of Stud/Apron along SM Bund at Mile 12/0 to 12/7 and Bakhri Loop Bund Mile 0/0 to 0/1 in Kandiaro Bund Sub Division.

02

Recouping of Stone Spurs Mile 142/3 and Stone Studs Mile 136/1 Along S.M Bund in Hala Division.

03

Rehabilitation/Reconstruction of Stone Apron and Stone Pitching Along SM Bund from Mile 70/7 to 72/0 in Moro Bund Sub Division.

04

Rehabilitation, Raising and Strengthening of spurs along Surjani Complex Bund, Sujawal.